Wallingford Infill – North Transfer Station & Touchstone North update

The foundation is in and the structure is rising at the North Transfer Station! The shoring in this photo is helping support that upper story while the concrete slab cures and then we should see it being framed fairly quickly.

These are structural bearing walls formed with wood and ready to be poured with concrete:

This is the lot next door – the Touchstone North Edge project I debuted a couple of months ago – and it has a foundation (the concrete is being protected with hardi-board to cure properly) and the orange pipes are where plumbing has been located…stubbed out, capped off and ready to be used for future connections at upper stories: